Quản trị kinh doanh - Chapter 7: Project time management


Developing the
Project Schedule

The project schedule is a chart that graphically depicts the sequence, interdependencies and start and finish times of the project.

The project schedule also depicts the activities to enable the identification of the critical path.

The project schedule allows for tracking time variances when the project is being executed

ppt26 trang | Chia sẻ: hongha80 | Lượt xem: 519 | Lượt tải: 1download
Bạn đang xem trước 20 trang nội dung tài liệu Quản trị kinh doanh - Chapter 7: Project time management, để xem tài liệu hoàn chỉnh bạn click vào nút DOWNLOAD ở trên
CHAPTER 7Project Time Management Developing the Project Schedule The project schedule is a chart that graphically depicts the sequence, interdependencies and start and finish times of the project.The project schedule also depicts the activities to enable the identification of the critical path.The project schedule allows for tracking time variances when the project is being executed. From Work Package To Network Activity-on-Node (AON) FundamentalsA = SequencesB = BurstC = MergeD = Parallel6–4 Sequence the Activities Add the Durations Carry out the Forward PassMaximum of Preceding Activities Carry out the Backward Pass Minimum of Succeeding Activities Calculate the Slack or Float Identify the Critical Path Free slack example Identify the Critical Path (cont.) The longest path through the activity network that allows for the completion of all project-related activities. The shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project. Extended Network Techniques to Come Closer to RealityLadderingUnder the standard finish-to-start relationship, when an activity has a long duration and will delay the start of an activity immediately following it, the activity can be broken into segments.The network can be drawn using a laddering approach so the following activity can begin sooner and not delay the work. Example of Laddering Using Finish-to-start RelationshipExtended Network Techniques to Come Close to Reality (Cont.)LagA lag directs a successor activity to be delayed.LeadA lead allows acceleration of a successor activity.Hammock ActivitiesAn activity that spans a segment of a project.Duration of hammock activities is determined after the network plan is drawn.Hammock activities are used to aggregate sections of the project to facilitate getting the right amount of detail for specific sections of a project.6–15Common Gantt Chart Relationships Moving the AON to a Project Schedule(See following slides) Finish-to-Start Relationship (FS) Start-to-Start Relationship Finish-to-Finish Relationship Air Control Project— Gantt Chart Options for Accelerating Project CompletionWhen resources are not constrainedCrashing The most common method for shortening project time is to assign additional staff and equipment (resources) to activities (crashing the project schedule) Outsourcing project workScheduling overtimeDo it twice, fast and then correctly Options for Accelerating Project Completion (cont.)When resources are constrainedFast tracking Sometimes it is possible to rearrange the logic of the project network so that critical activities are done in parallel (concurrently) rather than sequentiallyCritical-chain project managementReducing project scopeCompromising quality Options for Accelerating Project Completion (cont.)When cost is the issue Reduce project scopeHave the owner take on more responsibilityOutsource activities or the whole projectBrainstorm cost-savings options Resource Allocation Methods Project Scope IntegrationKey TermsactivityActivity-on-Arrow (AOAActivity-on-Node (AON)burst activityconcurrent engineeringcrashingcritical pathdanglerfast-trackingfree slackGantt charthammock activityheuristicladderinglag relationshiplagslevellingmerge activityparallel activity parallel/sequence activitiespathresource-constrained projectresource-constrained schedulingresource smoothingsensitivityslack/float (total) splittingtime-constrained project

Các file đính kèm theo tài liệu này:

  • pptpearson1e_ppt_ch07_4732.ppt